Smart hands job time estimator

A job time estimate adds up minutes per task, applies a contingency percentage and adds return travel. Every rate is editable and listed in the method section. Times only. This tool never shows prices or rates.

Enter your task quantities below. Everything is calculated in your browser from what you type.

Your job

Tasks

Site induction and sign-in

30 min per visit

Rack-mount 1U device

15 min per device

Rack-mount 2U+ device

25 min per device

Patch and label a cable

4 min per cable

Fibre clean and inspect

3 min per connector

Optic swap

5 min per optic

Drive swap

10 min per drive

Photo documentation

15 min per visit

Visual audit

2 min per RU

Console session and basic config

20 min per session

Packing for RMA

20 min per item

Allowances

Doubled for the return trip.

Total time including travel

1h 0m

0m on site plus 1h 0m travel.

On-site time
0m
Contingency
0m
Travel
1h 0m

Times only. This tool never shows prices or rates.

How this is worked out

Every rate is shown and editable. An estimator with hidden rates is not a tool.

On-site time is the sum of quantity times minutes per unit across all tasks. Contingency defaults to 20 percent. Travel is doubled for the return trip.

Task rates are starting values for planning. Actual times vary by site, access and complexity.

Questions

What does this tool do?

This tool helps engineers with smart hands job time estimator. Enter your own figures and everything is calculated in your browser.

Are my figures stored?

No. The calculation runs in your browser and nothing is sent to us.

How accurate is it?

It is exactly as accurate as the figures you put in. Treat it as a planning aid, not a precise measurement.

Is it free?

Yes. All DataOptix engineer tools are free with no login, no email gate and no cookies.

Do this kind of work? Join the DataOptix engineer network.

Vetted independent engineers. Scoped jobs, no bidding.

Apply now

Need this work done?

Tell us the site, the task and the urgency. A coordinator replies within 2 business hours.